Planned Program Timeline

Please see the planned program timeline for the NextGen Energy Program below. The timeline is subject to change as the NextGen Energy Program continues to progress and new information becomes available. (Updated 2023)

  • October 2018 Kick off meeting with university stakeholders and student leaders 
  • 2019 Ongoing collaboration with university stakeholders and student leaders 
  • April 2020 Approved by the Maryland Board of Public Works
  • Fall 2021 Competitive procurement process with shortlisted proposers  
  • June 2022 Two finalists selected; start of the Best and Final Offer stage of the procurement process
  • 2023-2024 Identify private sector energy company and secure partnership approval from Board of Public Works 
  • 2024 and Beyond NextGen Implementation: Existing system maintenance and improvements; new system construction