Please see the planned program timeline for the NextGen Energy Program below. The timeline is subject to change as the NextGen Energy Program continues to progress and new information becomes available. (Updated 2023)

  • January 2020 Pre-solicitation report submitted to the State
  • Spring 2020 Approved by the Maryland Board of Public Works
  • Summer 2020 Request for Qualifications 
  • Fall 2020 Shortlist qualified proposers
  • Fall 2021 Request for Proposals
  • Spring 2022 Best and Final Offer stage of the procurement process
  • Spring 2023 Select private sector energy company to complete the work
  • Fall 2023 Submit proposed transaction terms to the Board of Regents, state legislative bodies and the Board of Public Works
  • Winter 2023 Financial close and transition of operations to new partner